Progress is being made on the big project; the last couple of work days have been spent putting things together instead of taking them apart.
The main effort is just a little short of half-way complete. That's good -- but today will be followed by a day and a half or rain, or possibly two full days. And near the very end of the tower work, we will need two or more custom-fit items that can't be made onsite; we've already called in measurements to the supplier and it's about fifty-fifty if they will be here before the rain.
Yesterday was another twelve-hour day, though I had to take three out and get to a regularly scheduled doctor's appointment, all the way downtown. At least it made a change in scenery.